The site for the west expansion to gob pile #2 (TR -72) will initially be cleared of <br />trees and heavy brush. Then, it is estimated approximately 4,100 cubic yards of <br />topsoil and approximately 60,900 cubic yards of coverfill material will be <br />salvaged. The salvaged topsoil and coverfill material may not be stockpiled, but <br />will likely be used to for reclamation of gob pile #2. <br />The area for the west and north expansion of gob pile #2 (TR -76) will initially be <br />cleared of trees and heavy brush. Then, if topsoil is available, approximately 11,810 <br />cubic yards and approximately 29,600 cubic yards of coverfill material will be <br />salvaged. The salvaged topsoil and coverfill material may not be stockpiled, but will <br />likely be used to for reclamation of gob pile #2. A topsoil variance was approved <br />with TR -76 and allows for a variance from topsoil removal in areas that are too <br />steep (slopes exceeding 2HA V), where the topsoil is too thin (less than three <br />inches), or where the material is too rocky. This request is specifically for the <br />planned disturbance associated with the expansion of Gob Pile #2. However, if <br />topsoil is available it will be salvaged. <br />TR -76 - 7 - 05/13 <br />