Laserfiche WebLink
located on a gentle slope to the south of the Area 1 Pit. These cuttings mixed with coal during conveyance from the <br />mine and therefore were typically washed to recover the coal. The cuttings and coal comprised an estimated 5 -10 <br />percent of the monthly volume of low quality coal processed through the wash - plant. The cuttings then became <br />part of the refuse stream coming from the plant. The fines generated during the washing process of the <br />cuttings /coal were discharged underground as part of the thickener underflow. The course fraction was placed in <br />the refuse pile. <br />Given the fact that the fines from the cuttings /coal were processed through the plant and the fines disposed of <br />underground in the thickener underflow, it was not necessary to conduct a geotechnical analysis of the material <br />going to the refuse pile. The fine fraction was the reason for committing to conducting a geotechnical analysis, but <br />they no longer will be placed in the refuse pile. <br />TCC test - washed some of the cuttings from the ventilation shaft boring but found it not to be very efficient. Based <br />on this, TCC generally hauled the remainder of the borings, unless they contain significant amounts of coal, to the <br />refuse pile for disposal. A geotechnical analysis of the cuttings was performed by NWCC and a copy of the <br />resulting report is presented in Exhibit 25a -2. It demonstrates that the cuttings can be placed in the refuse pile <br />without adversely impacting stability. <br />Once the cutter -head broke - through to the surface within the shaft collar, the cutter -head, drive unit, and temporary <br />headframe were disassembled and removed from the site. A permanent shaft casing consisting of steel ring -beams <br />and liner -plate was placed, and the annulus between the liner and the shaft bore was cemented in segments. <br />The cement shaft liner serves to isolate the Twentymile Sandstone from the Wadge Overburden. Additionally, the <br />Twentymile Sandstone was pressure - grouted to prevent seepage into the shaft, providing further assurance that, <br />after final closure, the water in this unit will be confined and not seep down on the inside of the shaft. Following <br />completion of shaft boring and casing operations and removal of equipment from the site, the fan enclosure (fan <br />shroud) and electrical control building were erected on the previously constructed concrete pads, and the fan, fan <br />drive motor, and electrical control, monitoring, and communication systems were installed. Average pad thickness <br />is 2 feet and total pad surface area is approximately 3100sf. The installed axial -vane exhausting ventilation fan has <br />a capacity of 800,000 cfm with a 3,000 hp drive motor. A fence was constructed to enclose the fan installation. <br />Following commissioning, the shaft pad site and access road were cleaned -up and surface areas graded and dressed. <br />In addition to the main vent shaft, up to two additional holes were cased to allow for power drops and other <br />ancillary uses into the mine. The two holes were cased to an internal nominal diameter of 4 and 8 inches. One of <br />the cased holes was used as a pressure relief /accumulator for the production mine water system. System pressure <br />relief and back -up were designed to prevent any surface discharge of production mine water, however, a <br />catastrophic failure of both primary and back -up pressure relief valves resulted in a discharge in mid -2005. A <br />manual ball valve was installed at that time to seal the casing and prevent any future discharge. If suitable system <br />pressure relief controls can be installed to assure that no discharge will occur, the manual valve may be removed or <br />replaced with a fail -safe valve that would allow for free movement of air in the pressure relief /accumulator pipe but <br />prevent fluid discharge, at some point in the future. So long as no discharge is anticipated or occurs, the provisions <br />of Rule 4.05.2 are not applicable. <br />The 4 -inch cased borehole has been disconnected from the mine water system, and will be used as a rock -dust drop <br />borehole. TC proposes to install an additional rock -dust tank over this existing borehole to supply rock -dust for <br />rock - dusting of the main entries and adjacent mine working areas. The proposed rock -dust tank installation is <br />within the existing NWM Ventilation Fan surface disturbance area, and will involve no new or incremental <br />disturbance. The NWM Rock -Dust Tank Installation will consist of a re -used rock -dust tank from the Empire Mine <br />property, which will be mounted on four 24 -inch diameter poured concrete piers extending approximately 22 feet <br />below ground level; a 5 x 5 x 1 foot concrete pad with baghouse dust collector unit; a connection to the existing <br />borehole; required electrical and control equipment, and 3 new powerpoles for a 280 -foot distribution line that will <br />tie -in to the existing NWM Substation (Primary Substation 12). The additional rock -dust tank installation can be <br />readily accessed from the NWM Ventilation Fan pad area and the existing NWM /6MN Light -Use Road. Drainage <br />for the existing NWM Ventilation Fan Installation is controlled by an existing Small -Area Exemption, and the <br />proposed rock -dust tank installation will not modify the drainage configuration or requirements. <br />MR10 -247 2.05 -45.2 09/24/10 <br />