Twi I M-le <br />Cat dozers cut the slope to rough grade near between stations A4 +00 to A6 +00, 610 +00 to B12 +00, F8 +00 to <br />F10 +00, and DD6 +00 to DD16 +00. <br />A John Deere 870 excavator loaded 740 haul trucks with shot rock from STA C6 +00. The material was transported <br />to the rip rap plant for processing. <br />A John Deere 870 excavator loaded 740 haul trucks with clay rejects. This material was transported for use as <br />structural fill between STA H28 +00 to H30 +00. The structural fill was placed and compacted per method <br />specification. <br />Note: An AMEC field professional monitored structural fill material temperatures placed within fill areas. Average <br />structural fill temperatures were above 32 °F. <br />Clay (SLF) Processing: <br />Cameron Site: No clay mining or processing occurred at the Cameron Site. Approximately, 244,860 tons of clay 1 <br />soil liner fill (SLF) material have been produced at the Cameron site. SLF produced from the operation remains <br />stockpiled at Cameron Site for future use. <br />Squaw Gulch Clay Borrow Site: Clay mining and processing took place at the Squaw Gulch Clay Borrow Site. <br />Approximately, 94,417 tons of soil liner fill material has been produced at the Squaw Gulch Clay Borrow Site to <br />date. <br />Underdrain System: <br />Secondary Underdrain: A Cat 320 excavator completed the tie -in to the previously constructed portion of <br />secondary underdrain near STA H2 +00. The underdrain was continued upslope approximately 100 feet. <br />Installation followed project specification. Construction of secondary underdrain is not complete in this area. <br />Primary Underdrain: A Cat 320 excavator reworked the underdrain trench between STA 14 +00 and 15 +00 to tie it <br />together. <br />Tree /Slash Grubbing and Clearing, Chipping: <br />No clearing or grubbing occurred. <br />B) Underground Workings <br />UG #6153: Previously filled with coarse shaft backfill; however, a cave -in occurred, requiring additional material to <br />be placed into the working. A Cat 330 excavator was used to fill the underground working with coarse shaft backfill. <br />Four (4) Cat 740 haul truck loads; 96 yd' of coarse shaft backfill material, was placed into the working. Backfill not <br />complete; remediation efforts to be continued. <br />UG #6274: Blasting of previously drilled underground working. <br />n) Storm Water Management <br />Best Management Practices (BMP) is being performed. Erosion control efforts took place during this reporting <br />period following any precipitation (snow removal and runoff from melting snow and ice). <br />Page 2 of 6 MLF.2 WF 22 March 2014.doc <br />