My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2014-02-05_REPORT - M1980244
DRMS
>
Day Forward
>
Report
>
Minerals
>
M1980244
>
2014-02-05_REPORT - M1980244
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 5:39:43 PM
Creation date
2/7/2014 8:15:32 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
REPORT
Doc Date
2/5/2014
Doc Name
Weekly construction quality assurance report WE 01/25/2014
From
Cripple Creek & Victor Gold Mining Company
To
DRMS
Email Name
TC1
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
10
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
amec�� <br />approximately 24 inch lifts. The lifts were compacted per method specification by a Cat CS56 smooth drum <br />vibratory roller. <br />A John Deere 850 excavator loaded 740 haul trucks with material removed at the base of the PSSA toe berm. The <br />material was hauled to the upper PSSA toe berm fill surface and was placed using a Cat D8 GPS dozer in <br />approximately 24 inch lifts. The lifts were compacted per method specification by a Cat CS56 smooth drum <br />vibratory roller. <br />A John Deere 1050J, a Cat D8t GPS, and a Cat D6 GPS dozer graded the slopes between stations HHO +00 to <br />HH2 +00 and FF4 +00 to FF8 +00. <br />A Cat D9 dozer removed the former highway pavement and prepared a drill pad below the Crib Wall near stations <br />B8 +00 to B10 +00. <br />A Cat dozer graded the slope near stations Q6 +00 to 010 +00. <br />Clay (SLF) Processing: <br />Cameron Site: No clay mining or processing occurred at the Cameron Site. Approximately, 244,860 tons of clay / <br />soil liner fill (SLF) material have been produced at the Cameron site. SLF produced from the operation remains <br />stockpiled at Cameron Site for later removal I use. <br />Squaw Gulch Clay Borrow Site: Clay processing took place at the Squaw Gulch Clay Borrow Site. <br />Approximately, 41,500 tons of soil liner fill material has been produced at the Squaw Gulch Clay Borrow Site to <br />date. <br />A Cat 980 loader was used to transport till from the mid portion of the clay borrow area to the lower portion for <br />processing. <br />Underdrain System: <br />Secondary Underdrain: No secondary underdrain was installed during this reporting period. Approximately, 5,064 <br />feet of secondary underdrain has been completed to date in the VLF. <br />Primary Underdrain: No work was performed on the primary underdrain during this reporting period. A total of <br />1,294.60 feet of primary underdrain has been completed. <br />Tree /Slash Grubbinq and Clearing, Chipping: <br />Tree removal occurred at the Drain Cover Fill (DCF) stockpile expansion area occurred. <br />B) Underground Workings <br />Confirmation drilling occurred at underground working UG #6302. Additional work will continue. <br />Two layers of geogrid and select structural fill were installed at Working UG # 6123. Work is to continue. <br />Working UG #6302 was excavated to a depth of 25 feet. The bottom of the shaft was not located and no timbers <br />were found, they were possibly removed during slope grading. What appears to be an alit was noted at the bottom <br />of the excavation trending in a northerly direction up- slope. Drilling will be required to further locate the adit. The <br />shaft was backfilled for safety and drilling access was provided. Work to continue. <br />Cemented rock fill was placed in Underground Working number 6087. <br />UG 6374 was prepped for a 2 -layer geogrid system. AMEC personnel approved the prepared subgrade for geogrid <br />placement. <br />Page 2 of 7 MLE2 WE 25Jan14.doe <br />
The URL can be used to link to this page
Your browser does not support the video tag.