Laserfiche WebLink
Trapper Response to Comment 31: As per the meeting on November 12, 2013, the issues regarding the <br />release of liability associated with the Phase Bond Release process as it relates to the PR7 Permit Revision <br />were addressed. See explanation for item # 27. <br />With the PR7 Bond Estimate, the K, L, & M Pit's regraded surface (P.M.T.) incorporates a lower elevation <br />drainage profile that facilitates a lower cost grading plan by reducing the overall volume required to bring <br />the area to a post mining topography which provides positive drainage for the worst case bond year <br />reclamation plan. This regrade design, combined with the dragline operation's placing the M and Q seam <br />interburdens "in pit" (as opposed to hauling this material to the Horse Gulch Fill with the truck/loader <br />operation) results in a lower volume of material required to backfill the worst case pit void. The truck/loader <br />operation is utilized to move material that is too distant for the dozer grading operations to cost effectively <br />push. This material is removed within the adjacent pit areas and does not take any material from the Horse <br />Gulch Fill as was planned in the PR6 Worst Case Bond Estimate (see item #33 for truck/loader operations <br />variance explanation). <br />32. The current cost estimate includes a cost for drilling and blasting the F Pit, Z -Pit, East A Pit and K- <br />Pit. The proposed estimate only includes a cost to drill and blast the highwall associated with K/G <br />Pit. Given that Phase I bond release has not occurred for the areas currently bonded for F Pit, Z Pit <br />and East A Pit and that disturbance did occur in these areas, the proposed cost estimate needs to <br />include a drilling and blasting the highwalls in F, Z and east A pit. Please revise the cost estimate to <br />include this cost. <br />Trapper Response to Comment 32: As per the meeting on November 12, 2013, the issues regarding the <br />release of liability associated with the Phase Bond Release process as it relates to the PR7 permit revision <br />were addressed (see item # 27 response). <br />There is no highwall reduction drilling and blasting required for F or Z dip pits in that these pits have both <br />been mined out, backfilled, and graded, and there is no final highwall to drill & blast. Therefore, no Drill & <br />Blast costs are included in the bond estimate. <br />With respect to F pit, there should never have been a highwall reduction drill & blast estimate submitted <br />with PR6, in that F pit's final cut (which was in the worst case bond year of 2012) tied in to the spoils of the <br />previously mined out Z strike pit on the east side of F pit. The last cut in F pit had spoil on both sides of the <br />pit (i.e., no highwall). <br />Z dip pit does not have a final highwall that requires drilling and blasting either. K strike pit intersects the <br />final mined out cut (# 12) of Z dip pit from the southeast. K pit has advanced northward beyond the Z dip pit <br />void which has been backfilled with the spoil generated from K pit mining operations. Thus, there is no <br />highwall requiring drilling and blasting, and therefore, no costs for these activities were included in the PR7 <br />bond estimate. <br />AE pit drilling and blasting costs were inadvertently left out of the original PR7 Bond Estimate submittal. <br />Approximately $75,000 has been included to cover the drilling & blasting costs for AE pit in the grading <br />section of the bond estimate as requested by the Division (enclosed Table A -5.1). <br />33. The current cost estimate includes a cost to regrade the K -Pit using a truck/shovel team. Table 1.4- <br />2 in the current permit indicates the volume of material necessary to move for this task is 5,644,528 <br />cubic yards. The proposed table A -4.4 indicates only 2,818,014 cubic yards of material is necessary <br />to complete this task. This is a reduction of 2,826,514 yards. It does not appear that K -Pit parcels <br />