R � ameO <br />South MSE Wall: <br />Leveling pad concrete form work construction and concrete pouring for the leveling pad occurred. <br />The slopes above the South MSE Wall and to the southeast of the wall were hydro - seeded. <br />A Komatsu mini excavator was observed removing tailings from behind the Crib Wall to expose the timbers for use on the <br />South MSE Wall facade. <br />If) Storm Water Management <br />Best Management Practices (BMP) is being performed. Erosion control efforts took place during this reporting <br />period following any precipitation. <br />CQA ACTIVITIES: <br />1) Field Activities: Observation of construction activities during this reporting period included: Production drilling and <br />blasting, VLF /PSSA cut to fill and compaction, South MSE wall leveling pad construction and near -by hydro seeding, <br />Underground remediation and confirmation drilling, clay (SLF) processing. <br />11) Laboratory Activities: Laboratory testing continued with Permeability, Particle Size Distribution, Atterberg Limits, <br />Moisture - Density, gradations and material classification and identifications and field material sampling were performed <br />during this reporting period. <br />SLF: Sample Numbers 70 -S and 71 -S were obtained during this reporting period. Note that samples with the suffix " -S" <br />indicate the material originated from the Squaw Gulch Borrow Site; sample numbers lacking the suffix are from the <br />Cameron Site. <br />DCF: Sample Numbers 39 and 40 were obtained during this reporting period. <br />General Project Items <br />Meetings and Discussions: The Weekly Project Status meeting was held on November 201� between CC &V, Ames, and <br />Amec. <br />Summary of Concerns: None <br />CC &V: Daily updates, reporting and scheduling are some of the tasks occurring between CC &V Projects, Amec and Ames. <br />Miscellaneous: Drilling continued for the closure drain hydro testing during the early part of the week. Hydro testing was <br />completed by November 2111 and the hydro -test boreholes were abandoned with bentonite grout by November 22°x. <br />Deliveries: None <br />CQA Monitor <br />Submitted by: Eric Lorenson Date: 23 Nov 2013 <br />Reviewed By: _ <br />Tim Burkhard <br />Project Resident Manager <br />Phone: 505.975.8655 <br />Approved By: jft1- f` /, . <br />Date: <br />Date: / 2 - 5 - /_j <br />Page 3 of 6 MLE2 WE 11.23.13.doc <br />