My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2013-10-31_HYDROLOGY - M1983194
DRMS
>
Day Forward
>
Hydrology
>
Minerals
>
M1983194
>
2013-10-31_HYDROLOGY - M1983194
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 5:35:09 PM
Creation date
11/15/2013 11:46:32 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1983194
IBM Index Class Name
HYDROLOGY
Doc Date
10/31/2013
Doc Name
P & A Reports
From
Daub & Associates, Inc.
To
DRMS & BLM
Permit Index Doc Type
Hydrology Report
Email Name
THM
GRM
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
16
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Cement Plug No. 4: On September 26, 2013, RRWS was onsite at 07:30 hours, warmed up the <br />equipment, ran in the hole and tagged the top of Cement Plug No. 3 at 535 feet MD GL. The <br />third cement plug resulted in 647 feet of cement in the hole. The drill pipe was pulled back to <br />530 feet MD GL prior to pumping Cement Plug No. 4. NW Ready Mix delivered the cement for <br />the fourth plug number (7 cubic yards mixed at 19 sacks per yard with 15% fly ash additive) at <br />08:35 hours on September 26, 2013. An accelerant (1% CaCI) was added to the cement onsite <br />(in the truck) prior to dumping. RRWS started pumping cement at 08:45 hours and finished <br />pumping 20 minutes later. Good cement was circulated to surface 15 minutes into pumping <br />and 1.75 yards was pumped away. It took 23.25 cubic yards of cement to plug back to <br />approximately 30 feet MD GL below ground level. The pump was hooked up to the water tank <br />and was pumped clean, with waste water going into the pit. While the pump was being <br />cleaned, the crew pulled out the remaining 17 joints of pipe and laid them down. The drill pipe, <br />hoses and plastic tub were cleaned. <br />On September 28, 2013, RRWS was onsite at 07:30 hours and warmed up the equipment. NSI <br />filled up the water tank for cleaning cement from the equipment. NW Ready Mix arrived on- <br />site at 08:20 hours. Approximately 0.5 cubic yards of cement was poured down the casing, <br />bringing the wet cement top off to surface. The top of the P &A cement plug in the 1 -3A well <br />was measured at 3.4 feet below GL after curing. <br />Conclusion <br />The Natural Soda, Inc. rotary - drilled vertical monitor well 1 -3A was successfully plugged and <br />abandoned on September 28, 2013. A total of 23.75 cubic yards (460 sacks) of Portland Type <br />II /V cement were pumped down hole to plug the well from a depth of 1,860 feet MD GL, above <br />where the cast iron bridge plug (CIBP) was set during previous recompletion, to near surface <br />(see attached P &A Diagram). The intermediate casing was cut off below surface, and a dry hole <br />marker was welded onto the well head prior to reclamation of the pad. <br />Daub & Associates, Inc. Page 3 of 3 1 -3A P &A Report <br />
The URL can be used to link to this page
Your browser does not support the video tag.