Schmidt placed additional Class 6 material on the Victor -side tie -in for final grading prior to upcoming pavement <br />operations scheduled for Sunday, October 131,, 2013. <br />South MSE Wall: <br />No progress occurred during this reporting period. Progress is waiting on leveling mat construction and timber <br />connection placement. <br />11) Storm Water Mana eg ment <br />Best Management Practices (BMP) is being performed, Erosion control efforts took place during this reporting <br />period following any precipitation. <br />CQA ACTIVITIES: <br />I) Field Activities: Observation of construction activities during this reporting period included: <br />topsoil haul, production drilling and blasting, Cut to Fill ADR Haul Road (HR), HWY 67 construction, Underground <br />remediation, clay (SLF) processing and Drain Cover Fill (DCF) production and processing. <br />11) Laboratory Activities: Laboratory testing continued with Permeability, Particle Size Distribution, Atterberg Limits, <br />Moisture - Density, gradations and material classification and identifications and field material sampling were performed <br />during this reporting period. <br />SLF: Sample No. 58 thru 59 was obtained during this reporting period <br />DCF: Sample No. 27 thru 28 was obtained during this reporting period, <br />General Proiect Items <br />Meetings and Discussions: Weekly Project Status meeting was held at 10:00am on October 91h between CC &V, Ames, <br />CDOT and Amec. Topics discussed were Safety, Schedule, Project Issues, concerns and planning. <br />Summary of Concerns: None <br />CC &Y: Daily updates, reporting and scheduling are some of the tasks occurring between CC &V Projects, Amec and Ames. <br />Miscellaneous: None <br />Deliveries: None <br />CQA Monitor <br />Submitted by: <br />Thorne M Clark <br />Project Resident Manag <br />Ph: 970.846.9337 <br />Approved By: <br />­`7 <br />Date: /, <br />Page 3 of 6 NILE2 WE 10.12.13.doc <br />