<br /> . PRELIMINARY. <br /> SUBJECT TO REVISION <br /> TABLE 4 <br />0 PROJECT COSTS <br /> (Thousand Dollars) <br /> (January 1982 Prices) <br />~ <br />CJ <br />~ Altprnativp. <br /> I II III IV <br /> Power Plant Mechanical- <br /> Electrical Equ;pment <br /> Turbine & Generator 482 713 990 1161 <br /> Plant Electrical Eqpt 257 319 396 416 <br /> Switchyard Eqpt 145 145 172 192 <br /> Miscellaneous 69 85 96 106 <br /> POWPT Plant - Civil Work 303 383 449 541 <br /> Switchyard - Civil Work 15 17 19 21 <br /> PpnRt.ock 20 20 20 20 <br /> Tr::tnsm;F;sion Linp (2 milp-s. 69kv) .J2. ....9.ll --9!i ----9!l <br /> Total Cost 1377 1772 2236 2556 <br /> Regional Cost Variance (90% ) 1239 1595 2012 2300 <br /> Cost with 25% Contingencies 1549 1994 2515 2875 <br /> Engr & Overhead Cost (19.5%) 102 389 ..--M!l. --3.QD. <br /> Total Project Cost 1851 2283 3005 3435 <br /> Interest During Canst (.07625) 141 182 --21.2. -..2U <br /> Total Investment Cost 1992 2565 3234 3697 <br /> <br />24 <br />