<br />Shasta Dam, the key storage unit, is more than 80 per cent complete. The
<br />present program calls for completion about June 15, 1944. A contract has
<br />been awarded for the fabrication of the lower tier tube valves at elevation 742
<br />and these are scheduled for delivery in the summer of 1943. A contract is in
<br />force for the fabrication of outlet bulkhead gates, with delivery scheduled for
<br />October, 1943. The spillway bridge is scheduled for delivery in November,
<br />1943. Drum gate embedded material installation is scheduled for June, 1943, to
<br />March, 1944. Completion of the dam and appurtenant structures for two-unit
<br />operation will require about 6,600,000 man hours. Additional tube valves and
<br />drum gates for 3, 4, 5 units for expanded power production will require about
<br />20 months after authorization for delivery and installment.
<br />Shasta Power Plant and Switchyard, as of February I, 1943, was
<br />within about one year of completion. The powerhouse building was 98 per cent
<br />complete. Two turbines, governors and generators have been delivered, and
<br />transformers were scheduled for delivery in 10 months. The War Production
<br />Board, however, has issued a "stop-work" order o~ all but two units of the
<br />power development program, and two generator umts have been transferred
<br />to Grand Coulee Dam and are now in operation there. .
<br />Keswick Dam, on which work began in October, 1941, was about 40 per
<br />cent completed at the first of this year. Concrete work on the dam will be con-
<br />tinued, but work on the power unit has been stopped by W.P.B. About a year
<br />and a half will be required to complete the dam and other structures for power
<br />generation, after work is resumed.
<br />Shasta-OrovilIe Transmission Line is in the construction stage. Con-
<br />gress has appropriated $400,000 for construction of a short line to connect
<br />with the Pacific Gas and Electric Company's Shasta sub-station near Cotton-
<br />wood. On July 20, Secretary Ickes ordered the Bureau of Reclamation to con-
<br />struct a 230 KV transmission line on wooden poles not only to Shasta Sub-
<br />station, but continuing on to Oroville, using unexpended balances. The cost
<br />of the entire line is $1,900,000.
<br />Shasta-Antioch Transmission Line and Antioch Steam Plant and
<br />Switchyard are in the stage of preliminary surveys and the preparation of
<br />plans and specifications. Actual construction cannot be undertaken until
<br />W.P.B. "stop-work" order is lifted and funds appropriated. No appropriation
<br />has been made for the steam plant except $200,000 for the preparation of plans.
<br />Delta Cross Channel has had preliminary surveys as to various routes,
<br />but no plans and specifications have been prepared; and no righ~s of way ac-
<br />quired. Four years would be necessary for economIcal constructIOn.
<br />The Contra Costa Canal system is completed over a distance of more
<br />than 37 miles and only 11 miles are left to finish, together with appurtenant
<br />structures, gates, etc. Work was suspended May 23, 1942, due to lack of pri-
<br />orities on materials. The main canal is 85 per cent completed.
<br />For the Delta.Mendota Canal, about SO per cent of the location surveys
<br />have been completed, but no rights of way acquired or plans and specific~tions
<br />prepared. Construction work will take about four years after thIS umt has
<br />been started.
<br />Friant Dam on the San Joaquin River is over 90 per cent completed, and
<br />ready for the installation of cranes, gates, and valves. This structure can be
<br />placed'in operation within about a year.
<br />
<br />J1EOZOO
<br />
<br />(8)
<br />
<br />I
<br />I
<br />
<br />J
<br />j
<br />
<br />Madera Canal, on which work began in March. 1941, has been com-
<br />pleted to the valley floor, a distance of about eight miles, and is 30 per cent
<br />complete. No work has been done on this since September, 1942, and about
<br />two years work will be required for its completion.
<br />Friant-Kern Canal has about SO per cent of the location surveys com-
<br />pleted, and specifications for the first six miles were issued, but no contract
<br />awarded. Plans have been completed for the next 24.4-mile section of the
<br />canal to Kings River, and specifications drafted for construction of Little Dry
<br />Creek siphon and the canal from mile 5.9 to mile 13.5. About 13 per cent of
<br />the right of way has been secured. According to the report of the U. S. Bureau
<br />of Reclamation, economical construction would require a minimum period of
<br />four years, but it would be possible to complete construction in two years, at
<br />an increase in cost of not less than 2S per cent. At present this unit is also
<br />under the W.P.B. ban on priorities for materials, and although recommended
<br />by the War Food Administration, recently has been refused permission of the
<br />W.P.B. for release of materials.
<br />
<br />Resumption of Construction on Water Supply Units
<br />On April 12 the Executive Officer and other representatives of the Cali-
<br />fornia Water Project Authority appeared before the Interior Sub-committee
<br />of Appropriations Committee of the House of Representatives and requested
<br />an appropriation for construction of various units of the Central Valley
<br />Project, urging particularly the resumption of work on the irrigation features,
<br />and emphasizing the advantages and needs for food production.
<br />The units on which the U. S. Bureau of Reclamation made resurveys and
<br />submitted revised lists of critical materials required were the Friant Dam, and
<br />Madera, Friant-Kern, and Contra Costa Canals. Studies were made in co~
<br />operation with the U. S. Department of Agriculture with regard to food which
<br />could be produced. It was found that in the case of Friant Dam, the installa-
<br />tion of about one-half of the gates and valves can be deferred, and those im-
<br />mediately necessary can be transferred from Boulder Dam thus reducing the
<br />metal required from 2600 tons to 1000 tons. It was estimated that needed
<br />supplemental water supplies could be produced, and over a million tons of food
<br />produced, including such essential war crops as potatoes, beans, flaxseed,
<br />grain sorghum, milk and beef.
<br />On May 10 the War Production Board announced its approval of re-
<br />sumption of construction on the Friant Dam and the Madera Canal. Comple-
<br />tion of the Contra Costa Canal" and construction of the Friant-Kern Canal
<br />were not acted upon at this time, but referred to the War Food Administra-
<br />tion for study and recommendation. Appropriations for the fiscal year 1944
<br />made by Congress are as follows:
<br />
<br />CONGRESSIONAL APPROPRIATIONS FOR CENTRAL VALLEY PROJECT
<br />(Fiscal Year Ending July, 1944)
<br />Shasta Dam, reservoir, and power plant......h......___nnuohmn...nun...n...n$10,900,OOO
<br />
<br />~i~':~c~~a~d~e~~~~[r.~~~.~:::::~:::::~:~~~::~~:::::~::::~:::~~::~:::::::~::~~::::::::~:::~~::: 1,t~t:~
<br />Transmission Line to Shasta Sub-station...____..............................,.......... 400,000
<br />
<br />~~t~~~f~~~it.~.l~tL~~t~~L:;;;;;;;;~;~:;~~;;;~;;:~~~~:~~~;~;~:~:~:~:~~~~~~~~~~~~ ;:iil
<br />
<br />TOT AL.m~.nm.~~..~~~~.~_m_._~_~~.m_mmm_.m__..nnmm n..mm~$22.569,OOO
<br />(9)
<br />
|