<br /> TABLE 5
<br /> PHASE I REIMBURSABLE COSTS - 1988 Method wlo Indirects
<br /> M&I CONTRACTORS
<br />Entity Acre Feet Contract Limit 1985 Cost 1993 Cost
<br />ALPWCD 9,200
<br />Const. 15,878,000 36,553,000
<br />IDC 3,616,000 15,883,386
<br />Total $33,140,000 $19,494,000 $52;436,386
<br />SJWC 30,800
<br />Const. 12,800,000 36,366,4/2
<br />IDC 14,537,097
<br />Total $16,640,000 $12,800,000 $50,903,509
<br />SUIT 26,500
<br />Const. 34,994,000 73,465,094
<br />IDC 14,203,000 38,298,067
<br />Total $82,959,000 $49,197,000 $111,763,161
<br />UMUT 6,000
<br />Const. 7,923,000 /6,632,000
<br />IDC 3,217,000 8,670,441
<br />Total $19,]61,000 $11,140,000 $25,302,441
<br />Navajo 7,600
<br />Const. 3,153,000 8,973,000
<br />IDC 1,148,000 4,439,512
<br />Total N/A $4,30] ,000 $13,412,5]2