<br />4-14 <br /> <br />Chapter 4 - Reallocations <br /> <br />weighted average update of all other project features. Costs are to be indexed from the <br />midpoint of the physical construction period to the beginning of the fiscal year in which the <br />contract for the reallocated storage is approved. Construction will be considered as having <br />been initiated at the start of the month when lands for the project were first acquired or on <br />the date when the first construction contract was awarded whichever was earlier. <br />Construction will be considered as having been completed at the end of the government <br />fiscal year in which final deliberate impoundment of the reservoir pool was initiated. <br /> <br />Use of Facilities Formula for Determininq Updated Cost of Storaqe <br /> <br />User cost = (Total Construction Cost (-) Specific Costs) x Storaae Reallocated (AF) <br />Total Usable Storage <br /> <br />In the above formula, "usable storage" does not include space set aside for sediment <br />distribution or for hydropower head.) <br /> <br />Example. For this example, the "Reallocation Report and <br />Environmental Assessment for Harry S. Truman Dam and Reservoir, <br />Missouri" will be utilized. This report was prepared by the Kansas <br />City District and is dated March 1994. This report is utilized <br />because it is an older project that requires updating by both the <br />ENR and the CWCCIS. This example, summarized in Table 4-8, updates <br />the Pomme de Terre Lake Project. <br />