<br />Chanee Order No. 5 and No. 6 - Preble's Habitat <br /> <br />The cost provided by the Contractor in Change Order No. 3 for the construction of the <br />mouse habitat indicated a cost of $4.01 per cubic yard to place 26,000 cubic yards for a total cost of <br />$104,173. It was understood that the Contractor's price per cubic yard was based on using on-site <br />material, but not dredge material. If the Contractor would choose to use dredge material to <br />construct the mouse habitat area, the $104,173 would be credited back the Town of Monument and <br />the Contractor would be paid based on the unit price for dredging, less a credit for disposing the <br />dredging material on-site. The Contractor elected to construct the habitat area with dredged <br />material. <br /> <br />Reduction in cost = $104.173 + $13,132.50 (credit) = ($117,305.50) <br /> <br />Per the terms of the Army Corps of Engineer's Individual 404 Permit and Biological <br />Assessment the Town of Monument was required to construct a portion of the new 25-foot wide <br />mouse habitat corridor just north of the southern line of Zone 4b, prior to May 15, 2002. Given <br />time restrictions imposed, the Town of Monument elected to have the work performed by the <br />Contractor to ensure that it was completed on time. <br /> <br />Additional cost = $3,108.24 <br /> <br />The following is a summary of all additional cost incurred by the Town of Monument and <br />its Contractor: <br /> <br />* Spillway Rehabilitation <br />* Chimney/Blanket Drain <br />* Upstream Gate <br />* Dredging . <br />* Borrow Material <br /> <br />Original Cost <br />Estimate <br />$&15,640 <br />$1,077,900 <br />$262,080 <br />$450,000 <br />$20,000 <br /> <br />Actual Cost <br />Incurred <br /> <br />Variance <br /> <br />Totals: <br /> <br />* Change Order No.1 <br />* Change Order No.2 and 3 <br />* Change Order No.4 <br />* Change Order No.5 and 6 <br /> <br />$2,625,620 <br /> <br />$0 <br />$0 <br />$0 <br />$0 <br /> <br />ASI -$2,775,060 $149,440 <br />$46,732 $46,732 <br />$317,409 $317,409 <br />$147,500 $147,500 <br />($114,198) ($114,198) <br />$692,460 $242,460 <br />$71,498 $71,498 <br />$167,245 $167,245 <br />$61,299 $61,299 <br />$153,750 $153,750 <br />$5,000 $0 <br />$4,323,755 $1,243,135 <br /> <br />* Design/Const. Engineering <br />* Environmental Engineering <br />* Land Acquisition <br />* Contract Contigency <br />* Prebbles Habitat <br />(Costs not included in Change Orders 3-6). <br />* Feasibility Report <br /> <br />$450,000 <br />$0 <br />$0 <br />$0 <br />$0 <br /> <br />$5,000 <br /> <br />Totals: <br /> <br />$3,080,620 <br /> <br />4 <br />