<br />Additional Cost = $287,000. <br /> <br />30" Steel Outlet Warks Installation: <br />Due to discrepancy between the original contract documents and the bid addendum, <br />additional work was required to complete the installation of the concrete mud matte located <br />beneath the full length of the 30" outlet pipe concrete encasement. <br /> <br />Additional Cost = $8,000. <br /> <br />Upstream Dam Face Rip Rap: <br />The pay item for Rip Rap was based on a per ton price, given an estimated specific gravity <br />of the rock to be imported. The actual rip rap imported to the site was heavier then <br />estimated, therefore increasing the overall tonnage quantity for the project. <br /> <br />Additional Cost = $300,000. <br /> <br />R.E. Monks Construction Company - Additional Cost due to Desil!n Chanl!es: <br /> <br />Additional Reservoir Storage: <br />Dili'ing excavauo1\-6filieresetV6ir atea'itwas determined that an additiona1700 acre-feet of <br />storage could be obtained by modifying the grading plan. Placement of the excess material <br />was negotiated by Consolidated Mutual to occur on adjacent property, making the design <br />change economical or approximately $2,000 per acre-foot. <br /> <br />Additional Cost = $1,300,780 <br /> <br />Asbestos Pipe Removal: <br />Prior to construction an abandoned asbestos water line was discovered on the reservoir site, <br />which was removed in accordance with OSHA guidelines. <br /> <br />Additional Cost = $39,910 <br /> <br />The cost overruns to-date associated with R.E. Monks work is $1,980,690 for an revised <br />total contract amount of $16,670,81 O. <br /> <br />Consolidated Mutual - Additional Costs due to Uuforeseeu Site Conditious. <br /> <br />24"-30" Watermain Installation: <br />During construction of the 24"-30" watermain from Fortune Reservoir to Fairmount <br />Reservoir, approximately 5-miles in length, a number of difficulties were encountered that <br />increased the overall cost ofthe installation. These problems areas included 11 complicated <br />ditch crossings, substantial unanticipated asphalt replacement in Indiana and McIntyre as <br />required by the State and County jurisdictions, time consuming and labor intensive traffic <br />control measures imposed by the State and County, and limited working hours from 8:30 <br />a.m. to 3:30 p.m. <br /> <br />Additional Cost = $1,500,000. <br />