|
<br />Benefit Cost Analysis
<br />
<br />Building Costs
<br />
<br />Table 1 delineates the construction costs associated
<br />with each building type, Costs are presented in terms of
<br />total building costs, per square foot costs, and average
<br />annual costs, The increased costs associated with flood
<br />proofing are highlighted, The detailed cost estimates
<br />from which these data were drawn are included in
<br />Appendix D,
<br />
<br />The total construction cost for the basic building is esti,
<br />mated at $562,812 or an average annual cost of $52,398
<br />over a 20 year period, On a square foot basis these
<br />costs total $25,01 or $2,33 annually for the 20 years,
<br />
<br />For the wet flood proofed building, the two major addi-
<br />tional costs are for glazed concrete block partitions in
<br />lieu of metal studs and drywall ($14,400) and the pre,
<br />mium for installing a waterproofed pit and a hoistway
<br />type elevator and associated penthouse in lieu of a
<br />hydraulic elevator ($1 0,000), Such wet flood proofing
<br />adds $46,915 to the cost of the total structure, or $2,09
<br />per square foot (when dispersed over the total square
<br />footage of the building), Since many of the flood proofing
<br />costs are incurred only for the ground floor construction,
<br />the taller and larger the building, the less flood proofing
<br />adds to the square foot cost of the building,
<br />
<br />For the building raised to one foot above the base flood
<br />on fill, the two major added costs are for the imported
<br />compacted fill material at $3.50 per cubic yard (a total of
<br />$12,530) and the addition of curved approach ramps
<br />with handrailings and retaining walls ($9,000), This
<br />method of compliance with the minimum rules and regu'
<br />lations of the National Flood Insurance Program adds
<br />$35,912 to the cost of the total structure, or $1,60 per
<br />square foot.
<br />
<br />For the partially raised building with watertight closures
<br />the primary added cost is for a 30 inch mat slab on fill in
<br />lieu of the 6 inch slab on grade ($33,750), The other
<br />relatively major cost is for a three inch layer of trowelled
<br />asphalt waterproofing below the mat slab ($11,250), The
<br />actual bulkheading adds only a $5,000 cost to the struc-
<br />ture, Overall cost is increased by $89,732 or $3,99 per
<br />square foot.
<br />
<br />When the building is elevated to 6 feet above the base
<br />flood on columns, certain cost items are added, but
<br />others are subtracted, The largest addilional cost is for
<br />the metal pan formed concrete suspended slab, includ,
<br />ing formwork, bracing, reinforcement, and finish
<br />($41,250). Other major costs are for: extending the core
<br />area to the parking area at the ground level, including
<br />stairs and elevator extension ($20,000); installing a
<br />
<br />18
<br />
<br />waterproofed pit and hoistway type elevator with asso-
<br />ciated penthouse in lieu of a hydraulic elevator
<br />($10,000); and providing more expensive foundations
<br />($10,000), Costs which are deducted from the basic
<br />structure, on the other hand, are for the slab on grade
<br />($12,000) and one set of entranceway stairs ($5,000),
<br />Overall, the cost olthe structure is increased by $87,923
<br />or $3,91 per square foot. For each of the elevated struc-
<br />tures, the additional cost per square foot is also reduced
<br />when costs are dispersed over a larger building, even
<br />though the costs of elevation, when spread over the
<br />greater square footage of the large structure, would
<br />decrease,
<br />
<br />In terms of additional construction cost, therefore, raising
<br />on fill is not only the least costly method of flood proofing,
<br />it also complies with the minimum regulations for the
<br />proposed building at the Jersey Shore site,
<br />
<br />There are several reasons why raising on fill was the
<br />least costly flood proofing method in this instance, The
<br />site is in an urban renewal area in which debris is mixed
<br />with a primarily sandy soil. Since compacted fill provides
<br />a better soil condition, raising on fill reduces foundation
<br />costs, In addition, the structure is iow,rise; raising on
<br />columns is not as economical because the cost cannot
<br />be dispersed over a large building, In other locations, for
<br />example where open space and parking areas are at a
<br />premium, there might still be an economic incentive for
<br />elevation on columns that leaves the ground level avail-
<br />able for other uses, In Jersey Shore, where the density
<br />of development is low and land is available and relatively
<br />inexpensive, such incentives are not present.
<br />
<br />Equipping the building with watertight closures was more
<br />costly, primarily because waterproofing the foundation
<br />makes the building buoyant, requiring use of a heavier,
<br />thicker slab, Indeed, if watertight closures had been in-
<br />stalled on a building at grade rather than the building
<br />raised three feet on fill, the cost would have been vir-
<br />tually prohibitive wilh a greater than 30 inch slab being
<br />required to counteract the buoyancy, As the building size
<br />and weight increase the structure eventually supplies
<br />sufficient dead load to counteract buoyancy without
<br />added depth and expense in the floor slab, Again, the
<br />relatively small size of the proposed commercial struc-
<br />ture becomes a critical factor in determining the most
<br />economical method of complying with National Flood
<br />Insurance Regulations,
<br />
|