<br /> <br />Federal Emergency Management Agency <br />Washington, D.C. 20472 <br /> <br />CERTIFIED MAIL <br />RETURN RECEIPT REQUESTED <br /> <br />IN REPLY REFER TO: <br />Case No.: 00-08-2l7P <br /> <br />The Honorable Noel 1. Busck <br />Mayor, City of Thornton <br />9500 Civic Center Drive <br />Thornton, CO 80229 <br /> <br />Community: City of Thornton, CO <br />Community No.: 080007 <br />Panel Affected: 0800lC0330 G <br />Effective Date of FEB 0 8 2001 <br />This Revision: <br /> <br />102-I-C <br /> <br />Dear Mayor Busck: <br /> <br />This responds to a request that the Federal Emergency Management Agency (FEMA) revise the effective <br />Flood Insurance Rate Map (FIRM) for Adams County, Colorado and Incorporated Areas (the effective <br />FIRM for your community), in accordance with Part 65 of the National Flood Insurance Program (NFIP) <br />regulations. In a letter dated April 19, 2000, Mr. Thomas C. Fairley, P.E., Principal Engineer, Kiowa <br />Engineering Corporation, requested that FEMA revise the FIRM to show the effects of placement of fill <br />and rechannelization of Niver Creek from just upstream of the confluence of Tributary L to <br />approximately 320 feet downstream ofInterstate Highway 25 (1-25), associated with the American <br />Furniture Warehouse development. This request also included a hydraulic analysis of an existing 8-foot <br />by 4-foot reinforced-concrete box culvert under 1-25. This request follows up on a Conditional Letter of <br />Map Revision dated October 17, 1997. <br /> <br />All data required to complete our review of this request were submitted with letters from Mr. Bill <br />DeGroot, P.E., Chief, Floodplain Management Program, Urban Drainage and Flood Control District; <br />Mr. Stephen Brown, Project Engineer, also with Kiowa Engineering Corporation; and Mr. Fairley. <br /> <br />We have completed our review of the submitted data and the flood data shown on the effective FIRM. <br />We have revised the FIRM to modify the floodplain boundary delineations of the flood having a <br />I-percent chance of being equaled or exceeded in any given year (base flood) along Niver Creek from <br />just upstream of the confluence of Tributary L to approximately 100 feet upstream ofI-25. As a result of <br />the modifications, the width of the Special Flood Hazard Area (SFHA), the area that would be inundated <br />by the base flood, for Niver Creek increased in some areas and decreased in other areas. All increases in <br />SFHA width occur within the American Furniture Warehouse property, and no insurable structures are <br />affected. The base flood is contained in the channel from approximately 250 feet upstream ofthe <br />confluence of Tributary L to approximately 400 feet downstream ofI-25. The modifications are shown <br />on the enclosed annotated copy of FIRM Panel 0800lC0330 G. This Letter of Map Revision (LOMR) <br />hereby revises the above-referenced panel of the effective FIRM dated August 16, 1995. <br /> <br />We will not physically revise and republish the FIRM and Flood Insurance Study (FIS) report for your <br />community to reflect the modifications made by this LOMR at this time. When changes to the <br />previously cited FIRM panel and FIS report warrant physical revision and republication in the future, we <br />will incorporate the modifications made by this LOMR at that time. <br />