<br />I TABLE IV-2 (CONTINUED)
<br />I PAGE 5 OF 5
<br />I Upstream of East 88th Avenue
<br />Item Quantity Unit Price Cost
<br />I Excavation, open, rural 2,300 cu.yd. 1.00 2,300
<br />Compacted embankment 150 cu .yd. 2.00 300
<br />I 18" riprap 2,200 tons 25.00 55,000
<br />Ri prap bedding 200 cu.yd. 10.00 2,000
<br />Gabions 775 cu .yd. 40.00 3LOOO
<br />I 66" CMP culvert 420Iin.ft. 65.00 27,300
<br />Miscellaneous Lump Sum 5,000
<br /> Subtota I 122,900
<br />I Contingency, 20% 24,580
<br /> Total Field Cost 147,480
<br />I Use S150,000
<br />I Project Summary
<br />I Land ,~"~
<br /> .,'
<br /> Engineering Acquisition- /-
<br /> \ I
<br /> Channel Reach Field Cost Legal & Admin. (8000 S/Acre) Total
<br />I S. Platte River to York St. 310,000 46,500 '--.c=-- 356,500
<br />I York St. to Explorador Calle 385,000 57,750 442,750
<br /> Explorador Calle to
<br />I Washington Street 9,000 1,350 10,350
<br /> Culvert at N. Valley Shopping
<br />I Center 305,000 45,750 350,750
<br /> Culvert North of E .84th Ave. 80,000 12,000 92,000
<br />I Channe I from E. 84th Ave.
<br /> to In terstate 25 65,000 9,750 48,000 122,750
<br />I Tributary L Detention 23,000 7,500 16,000 46,500
<br />I Niver Creek Detention 435,000 65,250 256,000 756,250
<br /> Upstream of E. 88th Ave. 150,000 22,500 176,000 348,500
<br />I Total Project Cost = 2,526,350