|
<br />. ,
<br />
<br />,
<br />
<br />,
<br />
<br />a
<br />
<br />830 P.2d 915. City of Thornton By and Through Utilities Bd. v, City of Fort Collins, (Colo. 1992)
<br />
<br />water at the Nature Dam.
<br />
<br />[17J We have already held that Thornton was on
<br />notice of the intent by Fort Collins to appropriate 55
<br />cfs of Poudre River Water from some point or points
<br />within the Corridor at least as of December 31,
<br />1986, the date on which the original application was
<br />filed. (FN7) The first and third *928 required
<br />functions were thus performed at least as of
<br />December 31, 1986. The issues now are whether
<br />the first and third functions were performed by a
<br />relevant act earlier than December 31. 1986, and
<br />when exactly was the second required function
<br />performed by a relevant act. The earliest date on
<br />which it can be said that the three functions were
<br />performed by relevant acts determines the
<br />appropriation date.
<br />
<br />To properly apply the first step test to these issues
<br />we begin with the appropriation date awarded by the
<br />water court and inquire whether the relevant act
<br />which was the basis of the appropriation date could
<br />have been deemed to have performed all three
<br />required functions, The relevant act was the formal
<br />adoption of the Plan by the Fort Collins city council
<br />on February 18, 1986, If adoption of the Plan
<br />performed none of the required functions, then it
<br />cannot be the basis for the appropriation date. The
<br />inquiry then would proceed to other relevant acts,
<br />possibly done before but most likely after February
<br />18, 1986, to determine the earliest date on which it
<br />can be said that all three functions of the overt act(s)
<br />prong of the first step have been performed.
<br />
<br />[18] Reviewing the evidence, we fmd that nothing
<br />in the Plan as adopted by Fort Collins could have
<br />placed Thornton or anyone else on notice that Fort
<br />Collins intended to appropriate water from the
<br />Poudre River pursuant to the Act. See S
<br />37-92-103(3)(a), 15 C.R.S. (1990). Nothing in the
<br />Plan indicates that a legal appropriation of water is
<br />required to implement the Plan, If anything, the
<br />testimonial evidence shows that an appropriation of
<br />water was not contemplated. If an appropriation of
<br />water were a condition precedent to the success of
<br />the Plan, then it surely would have received a
<br />modicum of specific discussion. Although the Plan
<br />does contemplate the enhancement of the natural
<br />environment, many land use plans implicate
<br />environmental issues, including water management
<br />and water habitat issues. without thereby constituting
<br />an intent to appropriate water under the Act.
<br />Conceding the otherwise laudable intent of the Plan.
<br />
<br />Page 13
<br />
<br />for purposes of the first step test it must fail as an
<br />act sufficiently overt as to have put interested parties
<br />on notice that a legal appropriation of Poudre River
<br />water was intended. (FN8) Thus, adoption of the
<br />Plan cannot be deemed to have performed either the
<br />first or the third required functions under the first
<br />step test. For the same reasons, the formal adoption
<br />of the Plan cannot be said to have performed the
<br />second required function of demonstrating that a
<br />substantial measure has been taken to apply water to
<br />beneficial use. Thus, we hold that Fort Collins did
<br />not take the first step toward appropriating the
<br />Poudre River water on February 18, 1986, the date-
<br />on which the Plan was adopted,
<br />
<br />[19] The water court cited a field trip by Fort
<br />Collins staff members at which photographs of what
<br />eventually would be the site of the Nature Dam were
<br />taken as confirming evidence of the formation of
<br />Fort Collins's intent to appropriate water as of
<br />February 18, 1986. That field trip did occur in
<br />February of 1986, but no more specific date is found
<br />in the record. Even if we were to assign the 18th as
<br />the date of the February 1986 field trip, such an act
<br />CQuld not be deemed to have manifested an intent to
<br />appropriate water or to have performed any other
<br />required function. See Bar 70, 703 P.2d at 1307-08
<br />(a field trip in the nature of a preliminary
<br />reconnaissance neither manifested an intent to
<br />appropriate water, nor demonstrated that a
<br />substantial measure was taken to apply waters to
<br />beneficial use, nor provided notice to interested
<br />parties) .
<br />
<br />The other relevant acts which the water court
<br />found to support an appropriation date of February
<br />18, 1986, occurred after *929 February 18, 1986,
<br />and as such cannot be deemed to establish the
<br />appropriation date of February 18, 1986. These
<br />post-February 18, 1986, acts were the posting of
<br />signs along the Corridor on December 31, 1986, and
<br />the publication in a local newspaper, also on
<br />December 31, 1986, of a notice to appropriate
<br />water. The dates of both acts coincide with the date
<br />of the filing of the original application for
<br />conditional water rights, an act which we have said
<br />performed the functions of manifesting intent and of
<br />providing notice to interested parties. It thus
<br />appears unlikely that the appropriation date can be
<br />set earlier than December 31, 1986, However, we
<br />remand this issue for a conclusive determination of
<br />the date on which the performance of all three
<br />required functions by a relevant act or acts
<br />
<br />Copyright (c) West Group 1999 No claim to original U.S. Govt. works
<br />
|