Laserfiche WebLink
Pisgah Reservoir and Ditch Company Agenda Item 12a <br /> July 15-16, 2015 Board Meeting(Updated July 17,2015) <br /> Page 3 of 4 <br /> TABLE 1: UPDATED PROJECT COST SUMMARY <br /> Task 2014 Updated <br /> Project Cost Project Cost <br /> Design Engineering $80,000 $141,000 <br /> Construction <br /> Phase I-Abandoned Outlet Works $90,000 <br /> Phase 11- Sluice Gate $240,000 <br /> Phase III- Gate Valves $441,000 <br /> Total $495,000 $771,000 <br /> Construction Management <br /> Phase I-Abandoned Outlet Works $48,000 <br /> Phase 11- Sluice Gate $72,000 <br /> Phase III- Gate Valves $96,000 <br /> Final Documentation $39,000 <br /> Total $70,000 $255,000 <br /> Contingency $100,000 $195,000 <br /> Total $745,000 $1,362,000 <br /> The Company can complete Phases I and II with the currently secured funds. As these two phases can <br /> be completed independently of Phase III, and each represent a safety improvement to the dam, CWCB <br /> staff has approved the Notice to Proceed for Phase I and II. CWCB staff will not approve the <br /> disbursement of loan funds for Phase III until the Company demonstrates it has the funds necessary to <br /> successfully complete Phase III. <br /> Schedule: The current construction schedule is as follows: <br /> Phase JUN '15 JUL`15 AUG '15 SEP `15 OCT `15 NOV '15 <br /> I -Abandoned Outlet Works ---- <br /> II -Sluice Gate <br /> III - Gate Valves --- <br /> Financial Analysis <br /> Table 2 provides a summary of the Project's financial aspects. The Company's blended interest rate of <br /> 1.75% for a 30-year term (Ownership: 93% agricultural, 7% low-income municipal), will remain as per <br /> the terms of the original contract. <br /> TABLE 2: FINANCIAL SUMMARY <br /> 2014 Approval Current Request <br /> Total Project Cost $745,000 $1,362,000 <br /> Borrower's Contribution $40,000 $40,000 <br /> WSRA Grant <br /> Arkansas River Basin $25,000 $25,000 <br /> Statewide $136,345 $136,345 <br /> TOTAL WSRA GRANT $161,345 $161,345 <br /> CWCB Loan Amount $543,655 $1,160,655 <br /> CWCB Loan Amount (Including 1% Service Fee) $549,091 $1,172,261 <br /> CWCB Annual Loan Payment $23,682 $50,559 <br /> CWCB Loan Obligation (Including 10% Reserve) $26,050 $55,615 <br /> Number of Shares 25,000 25,000 <br /> Annual Cost Per Share for Loan $1.04/share $2.22/share <br /> Current Assessment per Share $3/share <br /> Future Assessment per Share $3/share <br /> Cost of Project per AF to Preserve Storage (2,192 AF) $340/AF $621/AF <br />