Laserfiche WebLink
West Reservoir and Ditch Company Agenda Item 27e <br /> November 19-20,2014 Board Meeting (Updated November 21, 2014) <br /> Page 3 of 4 <br /> Alternative 2 - Rehabilitate dam: The project comprises three elements: safely emptying the <br /> reservoir without using the existing damaged outlet pipe, engineering design, and construction. <br /> The Company has already emptied the reservoir using pumps and temporary piping over the <br /> dam. The Company will hire a contractor to excavate through the dam to remove the existing <br /> outlet conduit, construct a new intake structure, place a new outlet works conduit, construct a <br /> new stilling basin, replace the embankment fill, and place upstream riprap slope protection. <br /> The cost of the Project is estimated to be $471,577 as shown in Table 2 below. <br /> TABLE 1: ESTIMATED PROJECT COST <br /> Task Description Amount <br /> Drain Reservoir $ 45,260 <br /> Construction $ 428,706 <br /> Engineering $ 42,871 <br /> Total $ 471,577 <br /> CWCB will disburse funds for Project related expenses at a rate of 50% loan to 50% grant for each <br /> invoice amount, up to the approved loan and grant limits. <br /> Schedule: Draining of the reservoir has already been accomplished; upon loan approval, the <br /> engineering design and bidding phase will commence, followed by groundbreaking in spring 2015, and <br /> construction completion targeted for fall of 2015. <br /> Financial Analysis <br /> The Company qualifies for a 2% agricultural interest rate for a 30-year repayment term. <br /> The Company was approved for a grant from the CWCB Water Supply Reserve Account (WSRA) in the <br /> amount of $225,658, contingent upon the approval of this loan application. Grant funds will be used <br /> for the borrower match requirement customary for a CWCB loan. The Company will cover any costs <br /> that exceed the estimated Project cost. <br />