Laserfiche WebLink
Left Hand Ditch Company Agenda Item 33a <br /> May 9,2014(Updated May 23,2014) <br /> Page 2 of 4 <br /> Background <br /> The Company, located in Boulder County, provides irrigation water to a service area of <br /> approximately 15,000 acres due north of Boulder. The service area follows Left Hand Creek from <br /> the Front Range foothills east to the Town of Niwot, and spans from the northern edge of Boulder <br /> Reservoir up to Foothills Reservoir. The Company owns and maintains five reservoirs used for <br /> storage and controlled release of the Company's water rights. <br /> Two of the reservoirs, Allen Lake and Lake Isabelle, were the subject of the original loan request. <br /> The work at Allen Lake was completed in 2013. Lake Isabelle is the subject of the request to <br /> increase the loan. <br /> At an elevation of nearly 11,000 feet, Lake Isabelle is the highest elevation reservoir in the Left <br /> Hand Ditch system. It lies within the Indian Peaks Wilderness which is operated by the U.S. Forest <br /> Service, and it is only accessible by foot or helicopter. At full storage, the capacity of the reservoir <br /> is 550 acre-feet. A rock tunnel is used to divert water through a mountainside to an outlet structure. <br /> The outlet structure consists of a gate valve located at the bottom of a 60-foot shaft. The gate valve <br /> is used to control release rates during the irrigation season and shut off releases to refill the <br /> reservoir during winter months. <br /> Project Update <br /> The Lake Isabelle outlet gate replacement was part of the original Project and was replaced in the <br /> 2013 construction season. Once the reservoir was drained for construction, the inlet structure to the <br /> outlet tunnel was inspected. The Company then discovered that additional repairs to the tunnel were <br /> necessary. <br /> Left Hand Excavating of Frederick, Colorado performed the construction at Lake Isabelle. With <br /> assistance from Smith Geotechnical, a plan to replace the inlet tunnel with a new 24-inch pipe was <br /> designed. The cost of the inlet tunnel repairs is estimated at$350,000. <br /> Schedule: Construction on Lake Isabelle is scheduled to resume in late summer of 2014,with <br /> completion expected by fall. <br /> Financial Analysis <br /> The Company qualifies for a blended (46% agricultural, 38%middle-income municipal, 16%high- <br /> income municipal) interest rate of 2.45% for a 30-year term. Table 1 provides a financial summary <br /> of the loan request. <br />