Appendix C <br /> Pipeline Cost Analysis <br /> ITEM UNIT COST UNIT NUMBE TOTAL REFERENCE NOTES <br /> Pipeline <br /> Pipe 36"80 psi SDR 17 $ 102 ft 26652 $2,718,504 HD Supply Freight Included <br /> Pipe Fittings $ 5 ft 26652 $ 133,260 Estimate <br /> Pipe Installation $ 10 ft 26652 $ 266,520 Estimate Joint Fusing and plat <br /> Zone Valves $ 25,000 each _ 4 $ 100,000 Estimate <br /> Str.Removal(Concrete Ditch) $ 40 c.y. 625 $ 25,000 Estimate <br /> Earthfill Existing Canal $ 5 c.y. _ 42650 $ 213,250 NRCS Cost Data Inflated 25%for fuel <br /> Trenching(adverse) $ 7.50 ft 8884 $ 66,630 NRCS Cost Data Inflated 25%for fuel <br /> Trenching(Regular) $ 5 ft 17768 $ 88,840 NRCS Cost Data Inflated 25%for fuel <br /> Select Backfill $ 25 c.y. 4500 $ 112,500 NRCS Cost Data Inflated 25%for fuel <br /> Highway Crossing $ 237.60 ft 160 $ 38,016 NRCS Cost Data <br /> Gravel Road Crossings $ 45_ft 160 $ 7,200 NRCS Cost Data <br /> Air Vents $ 600 each 20 $ 12,000 Waterman Ind. <br /> Pressure Relief Valves $ 1,000 each 4 $ 4,000 Waterman Ind. <br /> Turnouts $ 1,200 each 44 $ 52,800 HD Supply Freight Included <br /> Fusing Machine $ 1,500 mo 10 $ 15,000 <br /> Fusing Technician $ 500 wk 40 $ 20,000 <br /> Subtotal $3,873,520 <br /> Turnouts <br /> Solar Powered Telemetry $ 10,600 each 13 $ 137,800 Timberline Electric Installed,grouped <br /> AC Powered Telemetry $ 7,550 each 13 $ 98,150 Timberline Electric Installed,grouped <br /> Flow Meter-6" $ 3,350 each 44 $ 147,400 Timberline Electric <br /> Valve-6"-Remote Control $ 3,465 each 44 $ 152,460 Rocky Mt Valve <br /> Valve Controller $ 2,653 each 44 $ 116,732 Rocky Mt Valve <br /> Valve Box with cover $ 1,100 each 44 $ 48,400 Estimate <br /> Subtotal $ 700,942 <br /> Structure <br /> Telemetry $ 8,850 each 1 $ 8,850 Timberline Electric AC powered <br /> Headgate $ 1,500 c.y. 10 $ 15,000 NRCS Cost Data Cold Weather <br /> Overshot Gate $ 1,500 c.y. 38 $ 57,000 NRCS Cost Data Cold Weather <br /> Overshot Gate $ 3.60 lb 9750 $ 35,100 NRCS Cost Data <br /> Overshot Gate Lift $ 25,000 each 1 $ 25,000 Fresno <br /> Central Control Station $ 15,000 each 1 $ 15,000 Timberline Electric Computer graphics <br /> Subtotal $ 155,950 <br /> Total Construction $4,730,412 <br /> Engineering/Inspection(7%) $ 331,129 <br /> Subtotal $5,061,541 <br /> Contingency(15%) $ 759,231 <br /> Total Project Estimate $5,820,772 <br /> 32 <br />