PCC Meeting — October 05, 2010 <br />Version: October 5, 2010 <br />i. Previous report — 99% <br />c. Earnings to date - $94,385,810 <br />i. Previous report — $93,971,324 <br />d. Contract Value - $93,518,917 <br />i. Previous report $93,118,917 <br />e. No modifications issued since last PCC <br />i. CCE transfer modifications — None <br />ii. Change order modifications — None <br />iii. Total value of modifications issued to date - $8,667,774 <br />(a). CCE transfers — $2,624,358 <br />(b). Change orders — $6,043,416 <br />iv. Fourteen undefinitized modifications pending finalization <br />v. Three Requests for Proposal pending <br />vi. Comparison of CCE to Contract Amount <br />(a). Current contract value — $93,518,917 <br />(b). Current contingency - $2,661,668 <br />(c). Field Cost current - $96,180,585 <br />f. Ridges Basin dam is 99% overall complete <br />i. Previously showed 99% complete <br />6. Durango Pumping Plant, Stage I ( #8008) <br />a. Percent complete — 95% <br />b. No modifications since last update <br />c. One undefinitized modification pending finalization <br />d. Two RFPs pending <br />e. Comparison of CCE to contract amount <br />i. Current contract value - $6,212,295 <br />ii. Current contingency - $0.00 <br />iii. Current field cost - $6,212,295 <br />7. Durango Pumping Plant, Stage II ( #8013) <br />a. Time elapsed — 100% <br />i. Previous report — 100% <br />b. Percent complete — 99% <br />i. Previous report — 99% <br />c. Earnings to date — $56,148,044 <br />i. Previous report — $55,686,014 <br />d. Current net contract value - $56,279,299 <br />i. Previous report — $56,247,736 <br />e. Four modifications issued since last PCC meeting <br />i. CCE Transfers — None <br />ii. Change Order Modifications <br />(a). #109 — Sewer Vent Pipe — $25,018 <br />1. This was to correct design flaws with the sewage ejector system, also <br />included is the installation of a roll up door on the EG room and <br />revisions to the elevator hoist room lighting. <br />(b). #110 — Obligation of funds — $0 <br />(c). #111 — Obligation of funds — $0 <br />(d). #112 — Additional Seeding — $6,545 <br />1. Additional topsoil and seeding outside the fence and berm 6. <br />5 <br />