PROGRESS REPORT (April 2011) <br />• Navajo Nation Municipal Pipeline <br />- Fruitland Reach <br />- Pipeline work completed <br />- City of Farmington Reach <br />- Pipeline work completed <br />- Extended agreement to 7/15/11 for paving due to winter shutdown <br />- Schedules 2 through 6 <br />- Utility locates, Surveys, & Pipeline construction are ongoing <br />- Nenahnezad Tank is complete w/ exception of painting <br />