The NCLPIC manages water in the Greeley No. 2 Ditch, delivering approximately
<br />37,500 acre -feet per year. The ditch level fluctuates throughout the irrigation season making it
<br />difficult and inefficient to serve all of the users, particularly those near the end of the system. In
<br />order to overcome fluctuations in the ditch, NCLPIC must run extra water to ensure that users at
<br />the end of the system are not shorted. In addition, the NCLPIC estimates that it is approximately
<br />10,000 ac -ft short of its current annual water requests, due to operational losses as well as the
<br />transfer of Colorado Big Thompson water out of the system. The intent of this project was to
<br />construct three reservoirs near Barnesville to equalize ditch flows, improve system efficiency
<br />(approx. 2,000 AF /year), and provide additional storage (approx. 2,500 AF /year) to meet
<br />demand. The proposed reservoirs will also provide a benefit to the comprehensive groundwater
<br />augmentation plan that the company is developing.
<br />FEASIBILITY STUDIES
<br />Smith Geotechnical Engineering Consultants of Fort Collins completed the feasibility
<br />study in accordance with CWCB guidelines. The study included an assessment of alternatives to
<br />address storage and operational deficiencies.
<br />Table 1 below is a brief summary of the major project elements selected and their
<br />estimated cost, as presented in the original feasibility study:
<br />Table 1. Opinion of Cost
<br />DISCUSSION
<br />The NCLPIC has completed all the items identified above, with the exception of Drury
<br />Reservoir. The NCLPIC does not plan on pursuing the design and construction of Drury
<br />Reservoir at this time. The original storage volume of Cornish Reservoir was estimated at 1,600
<br />acre -feet, but was increased to 3,000 acre -feet during construction. The increased storage
<br />volume achieved in Cornish Reservoir eliminated the immediate need to construct the 600 acre -
<br />foot Drury Reservoir.
<br />The land necessary to construct both Drury and Cornish Reservoir was purchased in 2003
<br />under a separate loan contract between NCLPIC and Cornish Plains Livestock, LLP for
<br />$1,409,649, with a 20 -year amortization, an annual payment of $122,843, and a 10 -year balloon
<br />payment of approximately $1,030,000. The purchase price of the land and accrued interest was
<br />included in the overall cost of the project, as indicated above in Table 1. When the project was
<br />presented to the Board in November of 2003, staff recommended a maximum loan amount of
<br />$7,200,000, which was 75% of the total project cost of $9,542,000. The purchase of the land
<br />was included the 25% cost participation from NCLPIC.
<br />2
<br />Item
<br />Estimated Cost
<br />1.
<br />Drury Reservoir
<br />$2,217,000
<br />2.
<br />Cornish Plains Reservoir
<br />$2,350,000
<br />3.
<br />Barnesville Equalizer Reservoir
<br />$922,000
<br />4.
<br />Jack Wells Pumping Station & Pipeline
<br />$1,632,000
<br />5.
<br />Property Acquisition
<br />$2,421,000
<br />Total:
<br />$9,542,000
<br />DISCUSSION
<br />The NCLPIC has completed all the items identified above, with the exception of Drury
<br />Reservoir. The NCLPIC does not plan on pursuing the design and construction of Drury
<br />Reservoir at this time. The original storage volume of Cornish Reservoir was estimated at 1,600
<br />acre -feet, but was increased to 3,000 acre -feet during construction. The increased storage
<br />volume achieved in Cornish Reservoir eliminated the immediate need to construct the 600 acre -
<br />foot Drury Reservoir.
<br />The land necessary to construct both Drury and Cornish Reservoir was purchased in 2003
<br />under a separate loan contract between NCLPIC and Cornish Plains Livestock, LLP for
<br />$1,409,649, with a 20 -year amortization, an annual payment of $122,843, and a 10 -year balloon
<br />payment of approximately $1,030,000. The purchase price of the land and accrued interest was
<br />included in the overall cost of the project, as indicated above in Table 1. When the project was
<br />presented to the Board in November of 2003, staff recommended a maximum loan amount of
<br />$7,200,000, which was 75% of the total project cost of $9,542,000. The purchase of the land
<br />was included the 25% cost participation from NCLPIC.
<br />2
<br />
|