Laserfiche WebLink
Platte River Recovery Implementation Program <br />Lower Platte River Stage Change Study <br />Invoice Progress Report <br />Period Ending August 29, 2009 <br />PRODUCTION: <br />Work completed during period ending August 29, 2009: <br />Completed 2D model calibration, and began interpretation and analysis of 2D model results. Began draft <br />of Protocol Implementation Report. <br />Work anticipated for next work period: <br />Complete Draft Protocol Implementation Report. Complete Second Progress Report for Field Work <br />Activities. <br />SCHEDULE: <br />Per the scope of services, the schedule is as follows: <br />Phase /Task <br />Description <br />Milestone Date <br />Phase I/Task I -F <br />Final Protocol Development Report <br />April 4, 2008 <br />Phase II /Task II -A <br />Data Collection and Field Work <br />July 30, 2009 <br />Phase II /Task II -B <br />Hydrology <br />Ongoing throughout project <br />Phase IUTask 11 -C <br />River Hydraulics and Geomorphology <br />Ongoing throughout project <br />Phase IUTask II -D <br />Interpretation and Analysis <br />Ongoing throughout project <br />Phase II /Task II -E <br />Draft Protocol Implementation Review Meeting <br />September 30, 2009 <br />Phase IUTask II -F <br />Final Protocol Implementation Report <br />December 31, 2009 <br />Total Authorized Fee = <br />Fee invoiced to date: <br />$210,000.00 <br />$166,513.11 <br />COMMENTS: <br />Anticipate attendance at Program TAC meeting tentatively scheduled for September 29, 2009 in Kearney. <br />SPECIAL CONSIDERATIONS: <br />None <br />