_ , <br />Our original schedule anticipated CWCB approval of the grant around December 30, 2009, with work to <br />commence in January — February, 2010. Because of several administrative delays impacting actual <br />receipt of the purchase order, work did not actually start until the first week in April. The District and <br />WM have made every effort to maintain the original schedule and to complete the Plan by the end of <br />December 2010, but at this time we believe adoption of the Plan will occur between the end of January <br />and the end of February 2011. This sixty day delay corresponds to the time elapsed between grant <br />approval (2/8/2010) and receipt of the Purchase order (3/26/2010). <br />Please call us with any questions you may have. <br />Respectfully submitted, <br />Security Water District <br />1�Oz, r /b4'. <br />Roy E. Heald, General Manager <br />