Laserfiche WebLink
March 14, 1996, carpenter crew sets forms for slab and covered work area. <br />March 15, 1996, placement is made on slab and covered work area. <br />Desirable Fish Return Pipe <br />February 27, 1996, contractor began and completed excavation and installation of 12-inch PVC <br />pipe from forebay wingwall to holding tank location. <br />Fish Return Pipe <br />March 4, 1996, contractor began installing 12-inch PVC fish return pipe and 6-inch PVC feeder <br />line pipe. <br />April 22, 1996, excavation and laying fish return pipe completed. <br />April 24, 1996, backfill of fish return pipe is completed. <br />Jib Crane Pad and Jib Crane <br />February 27, 1996, carpenter crew set forms for 7'X7'X4' crane pad. <br />February 29, 1996, contractor places concrete for crane pad. <br />March 3, 1996, carpenter crew strips forms from crane pad placement. <br />March 27, 1996, jib crane base and trolley beam installed. <br />April 30, 1996, jib crane installation completed. <br />City of Grand Junction's 18-inch Waterline Relocation <br />December 18, 1995, Cat D6 dozer begins excavation for relocation of City of Grand Junction's <br />18-inch waterline and 2-inch filler line. <br />Const-11