SCHEDULE <br />Scope of Work activities related to field investigations for environmental permitting <br />studies were initiated during the summer of 2002, followed by engineering, geotechnical <br />and design studies which were initiated in 2005. The start dates and scheduled <br />completion dates for each task are delineated below. <br />Eagle Park Reservoir Enlargement Project Schedule <br />Task Description <br />Design Engineering & SEO <br />1 App. <br />Start Finish <br />Responsible Party Date Date* <br />Brown & Caldwell 1/1/OS 10/31/07 <br />2 Geotechnical Investigations GEI Consultants <br />Hydrosphere/Miller/ <br />3 Environmental Permitting Steffens <br />Porzak, Browning & <br />4 Legal Agreements Bushong <br />Western States <br />5 Survey and Legal Descriptions Survey <br />6 Project Construction To be determined <br />6/1/05 10/31/07 I <br />8/ 1 /02 10/31 /07 ~ <br />1/1/OS 10/31/071 <br />5/1/06 10/20/07 <br />6/ 1 /07 1 /31 /08 <br />*Revised Schedule personal communication with Dennis Gelvin, 5-14-07 <br />5 <br />May 16, 2007 <br />