Laserfiche WebLink
<br />Black Dike Pipeline Company <br />May 14, 2007 (Revised May 23, 2007) <br />Page 3 of4 <br /> <br />Agenda Item 3a <br /> <br />Financial Analvsis <br /> <br />Table 1 shows a summary of the funding sources for the project. The total estimated cost of the <br />project is $598,000. The construction will be funded by NRCS at approximately 65% after the <br />Project is complete. Therefore, the initial loan amount (during construction) is $598,000, based <br />on 100% of the estimated total Project cost (Per Policy #11). The loan will be reduced to <br />$207,000 after the Project is complete and the Company receives $391,000 from NRCS. <br /> <br />Funding Source Grant Loan <br /> Initial Loan Phase <br /> - <br />NRCS Construction Cost Share - - <br />CWCS Loan - $598,000 <br />Company - - <br />Total ($598,000) $ $598,000 <br />Post-Construction Loan Phase <br /> - <br />NRCS Construction Cost Share $391,000* - <br />CWCS Loan - $207,000 <br />Company - - <br />Total ($598,000) $391,000 $207,000 <br /> <br />Table 1. Project Funding Sources <br /> <br />* Received after construction is complete from NRCS Salinity Control Funds. <br /> <br />Table 2 shows a summary of the financial aspects of the Project. A CWCS Loan of $207,000 <br />will have an annual payment of $13,700 ($10,280 for the annual loan payment and $3,420 for <br />the reserve account during the first three years - see loan conditions below) under the loan <br />terms of 2.85% per annum for 30-years. The blended rate is due to part of the project irrigated <br />lands do not qualify as agricultural production land as defined by NRCS. Not considering the <br />loan reserve, the annual loan payment represents a loan cost of $10.25 per acre-foot for the <br />Project based on an average annual delivery of 1003 acre-feet of water. Since all other funding <br />for the Project is in the form of NRCS grants, the Company would have no other debt service on <br />this Project. <br /> <br />Table 2. Financial Summary of Project <br /> <br />Total Project Cost $598,000 <br />Project Construction Cost $598,000 <br />CWCS Post-construction Loan Amount $207,000 <br />Annual Loan Payment Amount $10,280 <br />Annual Loan Obligation (including debt reserve funding) $13,700 <br />Annual Project Cost per acre-foot (based on 1003 acre-ft) $10.25/ac-ft <br /> <br />Creditworthiness: The Company was incorporated in March of 2007 for the purpose of <br />undertaking the Project and therefore has very little financial history. The Company has no <br />existing debt. Repayment will be accomplished by member assessments according to the <br />Company's Funding Agreement. <br /> <br />Table 3 shows the Financial Ratios for the Company. The Company proposes to assess the <br />nine members according to the prorated amount of the decreed flows owned in the pipeline. The <br />