<br />Tal* 1 <br />Pickering Reservoir. Pl'8limlnary Conutructlon Estimates <br /> <br /> (Engineers Estimate) <br />Item WORK DESCRIPnON Quantity Quantity Unit Cost Costs <br />No. Units $/unit $ <br /> A - General PI'8D8ration <br />A1 Mobilization/Demobilization 1 LS $10,000 $10,000 <br />A2 Grubbing; Log Timber from Right Abutment 0.5 Acres $10,000 $5,000 <br />A3 Remove Existina Pond Dike and AoDUrtenances 1 LS $8,000 $8,000 <br />A4 <br /> Subtotal A 523000 <br /> B- Earthwork <br />a 1 StriP Foundation and Abutments 8600 CY $2.00 $17,200 <br />82 Excavation for Cutoff TrenrJI 1900 CY $6.00 $11,400 <br />83 Borrow, Haul end Place Zone 1 Fill for Cutoff Trench 21110 CY $10.00 $21,000 <br />84 Borrow, Haul and Place Fill for Oem Embankment 87900 CY $5.00 $439,500 <br />85 Furnish, Haul and Place Sand Filter Blanket and Chimney Drain 1700 CY $25.00 $42,500 <br />86 Furnish and Install4-inch PVC Toe Drain Piping 400 LF $7.00 $2,800 <br />137 Borrow Haul and Place Riprap Bedding 400 CY $25.00 $10000 <br />138 Borrow. Haul and Place RipraD Slape Protection 1200 CY $30.00 $36 000 <br />139 Furnish and Place Gravel Surfacing on Crest 150 CY $20.00 $3,000 <br />B 10 Place ToPSOil on Do.vnstream Slope 1 LS $6,000.00 $6,000 <br /> SubtotalS $580 400 <br /> c - Outlet WOIks <br />C 1 Foundation Preoaration Clean Bedrock, Place Zone 1 Fill 1 LS $8,000.00 $8,000 <br />C2 Furnish and Place Structural Concrete for Pipe Support 55 CY $400.00 $22,000 <br />C 3 Furnish and Install 21-inrJI Reinforced Concrete Pipe 290 LF $30.00 $8.100 <br />C4 Install Sand Cutoff Filters (2) with 4-inrJI PVC Drain 2 LS $1,000.00 $2,000 <br />C5 Furnish Concrete and Construct Outlet Works Intake Structura 8 CY $500.00 $4,000 <br />C6 Furnish Concrete and Construct Outlet Works Tenninal Structure 4 CY $500.00 $2 000 <br />C7 Furnish and Install 21-inch Control Gate with Ooerator 1 LS $6,000.00 $6,000 <br />C8 Furnish and Install JiJr Vent Piping, Trashrack and Other <br /> Miscellaneous MetalwortI 1 LS $2,500.00 $2,500 <br />C9 Construct Operator Pedestal and Stem $uPPOl't8 2 CY $500.00 $1,000 <br />C 10 Construct Outlet Ditch 1 LS $2,500.00 $2,500 <br /> Subtotal C 558 70D <br /> D- Service SPIllway <br />o 1 Excavation for Pipe Spillway 200 CY $10.00 $2,000 <br />02 Furnish and Install 24-inch ADS Service SPillway 220 LF $25.00 $5,500 <br />03 Backfill for Pipe Spillway 150 CY $10.00 $1,500 <br />04 Furnish and Install RiDI80 Armoring at Terminus 20 CY $30.00 $600 <br />05 Furnish Concrete and Construct Spillway Control Wall 1.5 CY $500.00 $750 <br /> Subtotal D 51600 <br /> E. Mlacellal'l8ous <br />E 1 Install Embankment Piezometers 6 Ea. $500.00 $3,000 <br /> <br />E 2 Install Movement Monuments <br /> <br />4 <br /> <br />Ea. <br /> <br />$125.00 <br /> <br />$500 <br /> <br /> Subtotal E $3,500 <br /> F - Engineeerlng and Inspection <br />F 1 ToPOar8DhiC Field Surveys 1 LS $10,000.00 $10,000 <br />F2 Geotechnical ExDIoratiOn - Soils Analvsis - Design Report 1 LS $25,000.00 $25,000 <br />F3 Feasibility AnalySis (CWCS) 1 LS $10,000.00 $10,000 <br />F4 Engineering Design, Including Hazard Classification, Flood <br /> Hydrology, Outlet Design, Spillway Design, Cost Estimates, <br /> Design Plans and Specifications 1 LS $25,000.00 $25,000 <br />F5 Bid Documents and Contract Negotiations 1 LS $2,500.00 $2,500 <br />Fa Field Construction Supervision and Insoeclion 1 LS $50,000.00 $50,000 <br />F7 Miscellaneous Fees 1 LS $2,000.00 $2,000 <br /> Subtotal F $124 500 <br /> <br />Option 2 <br />Crest Elevation: 990 <br />Spillway EleYation; 980 <br />Emergency Spillway: None: Store PMF <br /> <br />A - General Preparation <br />B - Earthwork <br />C - Outlet Works <br />o ,. Emergency Spillway <br />E - Miscellaneous <br />Subtotal <br />Contlng&ncy@ 15% <br />Total Construction <br />F - EngIneering and Inspection <br />Total Project Cost <br /> <br />$23,000 <br />$580,400 <br />$58,700 <br />$9.600 <br />$3,500 <br />$675,200 <br />$101,280 <br />$776,480 <br />$124,500 <br />$100,980 <br /> <br />December 10, 2002 <br />