<br />I <br />I Table 9 <br /> W <br />I Preliminary Opinion of Probable Phased Construction Cost <br />May 19, 2004 <br /> City of Lamar Secondary Supply <br />I Pressurized Transmission System <br />Phase 2 <br /> UNIT TOTAL <br />I ITEM DESCRIPTION QUANTITY UNIT COST COST <br />STORAGE AND PUMP SYSTEMS <br />I Phase Two <br />Ballfield Pump Station (7,714 GPM @ 90 PSI) 1 LS $200,000.00 $200,000 <br />Intake system, building, and electrical 1 LS $100,000.00 $100,000 <br /> Ballfield Storage Pond (42.62 acre-feet) 75,633 CY $1.50 $113,450 <br />I Pond Liner 1 LS $5,000.00 $5,000 <br />Aeration and Ozone System 1 LS $50,000.00 $50,000 <br /> SUBTOTAL. PUMP SYSTEMS AND STORAGE $468,450 <br />I TRANSMISSION SYSTEM <br />4-inch C900 PVC 2,911 LF $10.00 $29,110 <br /> 6-inch C900 PVC 0 LF $15.00 $0 <br /> 8-inch C900 PVC 0 LF $20.00 $0 <br />I lO-inch C900 PVC 0 LF $25.00 $0 <br />12-inch C900 PVC 3,464 LF $25.00 $86,600 <br />14-inch C905 PVC 0 LF $32.00 $0 <br /> 16-inch C905 PVC 0 LF $32.00 $0 <br />I 18-inch C905 PVC 770 LF $35.00 $26,950 <br />20-inch C905 PVC 1,380 LF $45.00 $62,100 <br />24-inch C905 PVC 0 LF $60.00 $0 <br /> 30-inch C905 PVC 275 LF $90.00 $24,750 <br />I 36-inch C905 PVC 0 LF $125.00 $0 <br />Pipe fittings - estimated at 10% of Total Pipe Costs 1 LS $22,951 <br />Isolation Gate Valves 1 LS $4,467 <br /> Blow-off assembly 4 Ea. $1,000.00 $4,000 <br />I Standard 2" Air-Vacuum Relief valve 2 Ea. $5,500.00 $11,000 <br />Pressure Reducing I Sustaining Valve Assemblies 1 Ea. $50,000.00 $50,000 <br /> SUBTOTAL - TRANSMISSION SYSTEM $321,928 <br />I DISTRIBUTION SYSTEM <br />2.5-inch CL 200 PVC 4,260 LF $7.50 $31,950 <br /> Pipe Contingency - estimated at 5% of Total Pipe Costs 1 LS $1,598 <br /> Pipe fittings - estimated at 10% of Total Pipe Costs 1 LS $3,195 <br />I Taps and Service Stubs at Single-family Residences 0 EA $1,000.00 $0 <br />Taps and Service Stubs at Non Single-family Residences 0 EA $2,000.00 $0 <br />Taps and Service Stubs at Institutions and Parks 1 EA $10,000.00 $10,000 <br /> Taps and Service Stubs at Commercial and Industrial 0 EA $1,000.00 $0 <br />I SUBTOTAL - DISTRIBUTION SYSTEM $46,743 <br /> TOTAL $837,120 <br />I Construction Contingency (7.5% of Total Construction Cost) $62,800 <br />Engineering Design Fees (6% of Subtotal) $50,200 <br />I IGRAND TOTAL $950,1201 <br />I Aqua Engineering, Inc. <br />and Colorado State University Secondary Supply Feasibility Study <br /> May 19, 2004 -38- <br />I <br />