<br />I COAL CREEK FEASIBILITY STUDY
<br /> ENGINEER'S OPINION OF PROBABLE PROJECT COSTS
<br />I ALTERNATIVE 5: UNDETAINED DIVERSION TO BOXELDER CREEK
<br />ITEM UNITS QUANTITY UNIT COST TOTAL COST
<br /> Excavation of canal to Boxelder Creek CY 80,000 $3 $240,000
<br />I County Road 66 Culverts EACH 2 $40,000 $80,000
<br />I County Road 6 Culvert EACH $40,000 $40,000
<br /> Precast Culvert Sections L.F, 150 $400 $60,000
<br />I For Railroad Crossing
<br />Concrete Ditch Transitions For CY 20 $150 $3,000
<br /> Railroad Crossing
<br />I Tunneling Under Rail Road LF 150 $500 $75,000
<br /> Concrete Drop at Boxelder EACH $20,000 $20,000
<br />I Creek
<br />Modifications to Existing LS $150,000 $150,000
<br /> Bridges at CR 64 and HWY 1
<br />I Modifications to Existing LS $125,000 $125,000
<br />Railroad Bridge South of HWY 1
<br /> New Bridge at CR 62 LS $150,000 $150,000
<br />I Boxelder Creek Channel LS $450,000 $450,000
<br />Improvements Through Town to 1-25
<br /> and bike trail {Excavation, seeding and biketrail}
<br />I Farm Land Right-of-way ACRE 20 $15,000 $300,000
<br /> Box Elder Creek Right-of-way Acquisition ACRE 30 $15,000 $450,000
<br />I Right-of-way Construction Permit LS $7,500 $7,500
<br /> SUlveying and Mapping {Box Elder Creek} LS $50,000 $50,000
<br />I Engineering LS $195,000 $195,000
<br />Legal LS $25,000 $25,000
<br />I FEMA CLOMR and Mapping LS $65,000 $65,000
<br />Road Repair SY 170 $25 $4,250
<br />I Traffic Control LS $25,000 $25,000
<br />Utility Crossings LS 12 $4,000 $48,000
<br />I Railroad Right-of-way permit LS $15,000 $15,000
<br />Subtotal $2,577,750
<br />I Contingency {at 25% of Subtotal} $644,438
<br />Total $3,222,188