<br />. . <br /> <br />Change Order No.7 - This change order reflects the removal of the S.H. 52 Channel Bid <br />Alternative "B" from the original contract. The S.H. 52 channel was re-bid to accommodate the <br />channel redesign and the relocation of various oil and gas lines in the area. As part of the redesign <br />the oil and gas company installed 3,300 l.f. of 4-inch steel oil/gas lines and 1,650 l.f. of 4-inch poly- <br />fiberglass oil/gas lines from their pressure wells to their collection facility. <br /> <br />Added Cost: s.H. 52 Channel = ($85,903), Utility Relocates = $41,921 <br /> <br />Total Construction Change Order Cost = $230,792 <br /> <br />Additional Professional Services - Letter of Map Revision <br /> <br />As part ofthe overall project the District needs to submit a Letter of Map Revision to FEMA <br />to formally revise the lOO-year floodplain for the communities of Frederick, Firestone, Dacono, and <br />the unincorporated Town of Evanston. The new regional detention pond removes the Town of <br />Frederick, Firestone and Evanston from the lOO-year floodplain. In order to have the lOO-year <br />floodplain officially revised all supporting technical data (hydrology, hydraulics, and design plans) <br />need to be submitted to FEMA for review and approval. The District has hired the services of <br />Rocky Mountain Consultants (Tetra Tech) to complete these submittal requirements. Upon <br />evaluation of the upper basin characteristics by the consultants it was determined that number of <br />improvements need to occur within existing developments to ensure that all stormwater flows reach <br />the regional detention facility. <br /> <br />Added Cost: Engineering = $50,000, Construction = $237,114 <br /> <br />The following is a summary of the actual cost incurred by the District and its Contractor: <br /> <br /> Original Cost Actual Cost <br /> Estimate Incurred <br />SEMA Construction <br />* Regional Detention Pond $1,471,720 $1,277,277 <br />* Change Orders $0 $230,792 <br />* Utility Relocates $20,000 $41,922 <br />Land Acauisition $350,000 $391,541 <br />Eneineerine Services <br />Regional Detention Pond $223,758 $441,276 <br />Letter of Map Revision <br />* Engineering $0 $50,000 <br />* Construction $0 $237,114 <br />Totals: $2,065,748 $2,669,922 <br /> <br />Based on the additional costs as illustrated above, the Tri-Area Sanitation District is <br />requesting 75% ofthe total additional project cost incurred, for an increased loan amount rounded to <br />$502,400, at their current interest rate of 5.00% <br /> <br />4 <br />