<br /> Beaver Creek Siphon Replacement Schedule <br /> UDdated ADril 28, 2003 <br /> 2003 <br /> Tasks Januarv Februarv March ADril Mav June July August Septembe October November December <br />1 Shareholder Approval (2/10/2003) X <br />2 Applv for Fundina (2/28 - 6/15/2003) <br />3 Feasibility Study (45 Days) <br />4 Fundina Inplace 6/15/2003 (105 days) <br />5 Geology Work (NRCS) (60 Days) <br />6 (Survey and Desian) 5/1 - 8/1/2003) 1/ <br />7 404 (b-1) Permit (60 Davs) <br />8 Select Contractor (30 Days) <br />9 Construction (60 Days Min.11/15/2003) <br />10) Float (30 Days) <br />1/ Work to include test pits (75 days). <br />