<br />"~O)~12 <br />U ..l.. \J ~ <br /> <br />Construction would begin after October 15th when irrigation diversions are no longer needed. <br />The Red1ands Power Canal would be dewatered to construct the canal bypass channel and install <br />the upstream and downstream bulkhead isolation structures. Once the bypass channel is <br />completed, RWPC could divert river flows to the Red1ands Power Plant to generated <br />hydroelectric power while screen construction continued. It is anticipated that the Redlands <br />Power Canal would be dewatered from October 15th to April 15th. Excavated material to <br />construct the bypass channel (about 50,000 cubic yards) would be wasted on-site in upland areas <br />identified by RWPC on RWPC's property, <br /> <br />Construction access would be from the existing dam and canal access road, No major road <br />improvements are anticipated. <br /> <br />8 <br />