Laserfiche WebLink
<br />Greeley Irrigation Company <br />January 23-24, 2007 <br /> <br />Agenda Item 9a <br /> <br />reasonable condition except for some downstream foundation repairs that are needed. . <br />The original work was done with wood pilings and the anticipated repair will consist of <br />removal of the pilings and pouring of a downstream concrete foundation wall. It is also <br />anticipated that broken up concrete from the existing diversion structure can be used as <br />riprap material. Currently, the structure is not capable of delivering decreed flows. <br /> <br />2. Hiqhwav 34 Structure Improvements - The structure at Highway 34 needs improvements <br />to create a suitable water surface level for gate deliveries while avoiding the risk of <br />overtopping. A solution to this problem has been conceptualized and probable <br />construction costs developed for an actuated gate to control upstream water surface <br />level. A long-crested weir is envisioned as well to allow excess flows to bypass the <br />structure in the event of a gate failure. <br /> <br />3. Pipinq and Canal Lininq Improvements - Piping and lining of the canal is considered to <br />be an improvement that could provide significant reduction of seepage and improve <br />canal operations. Several alternative pipe materials are under consideration and piping <br />is being compared to lining from the cost and longevity standpoints. Pipe materials <br />selected for analysis were aluminized steel pipe, HOPE pipe, reinforced concrete pipe, <br />PVC, and ductile iron pipe. The analysis of the different piping systems looked at the <br />ease of installation, flow characteristics, durability, and cost of materials. It was <br />concluded that the most optimal pipe material would be HOPE pipe and Ultra-Flow <br />aluminized steel pipe. These pipe materials are very different and have different <br />characteristics. Final selection of the material for each reach to be piped will be made <br />during detailed design. <br /> <br />4. Tree Removal - Large trees adjacent to the canal have been undercut over time by . <br />water flowing in the canal. Tree limbs clog the canal and a toppled tree could shut down <br />canal operations at critical times. It is proposed that the worst case condition of <br />undercut or diseased trees be removed. Trees will be marked, the removal work will be <br />competitively bid, and work will be contracted with one or more tree removal companies. <br /> <br />5. Headqate Repair, Replacement. or New Installation - The Soard and the superintendent <br />have identified locations where old, unused headgates will be removed. In other cases <br />headgates need repair or new headgates/flow measurement devices must be installed. <br /> <br />ifhe GIC Soard and the superintendent have broken the various discrete cost elements of the <br />project into three rankings for priority - Year 1 (highest priority), Year 2 (moderate priority), and <br />~ear 3 (lower priority). Year 1 (highest priority) improvements total $783,600, Year 2 <br />(moderate priority) improvements total $1,064,000, and the Year 3 (lower priority) improvements <br />total $609,900 for a total of $2,457,500. <br />I <br />he Total Project cost is summarized as follows: <br />1. Engineering Design <br />2. Construction (ine!. contingency) <br />TOTAL <br /> <br />$ 271,900 <br />2,185,600 <br />$2,457,500 <br /> <br />Schedule - The project will be implemented over a multi-year period, generally between Spring <br />I <br />.2007 and Spring 2009. If the loan is approved by the CWCS, design would start in April -July <br />I <br />2007 for those items requiring engineering and construction documents. Construction for these . <br />items would start as soon as the canal is shut down in the Fall of 2007. Repair and partial <br />~eplacement of the GIC river diversion is expected to occur between October 2007 and March <br /> <br />40f6 <br />