<br />. <br /> <br />. <br /> <br />Activity 11e - Prepare Interim Report - Work on this <br />activity has essentially been completed as drafts of <br />revised chapters for the Interim Report were submitted to <br />the Colorado Water Conservation Board during the period. A <br />draft of the complete Interim Report was delivered to the <br />Board on July 16, 1982. <br /> <br />3. Budget and Expenditures <br /> <br />The cumulative expenditure schedule for the project is <br />attached as Attachment C. Actual expenditures for the month of <br />June 1982 totalled $36,372 as compared to a projected amount of <br />$17,554. Total expenditures through June are $234,587 as com- <br />pared to a projected accumulative amount of $160,268. <br /> <br />NBID-965-5-SRNOG <br /> <br />G <br />